When:
July 28, 2019 all-day
2019-07-28T00:00:00-06:00
2019-07-29T00:00:00-06:00

Beginning Wednesday, July 17, 2019 through Wednesday, July 31, 2019 milling & overlay will begin on the following streets:

  • 13th Street from ‘U’ Street north to Dead End,
  • “N” Street from 10th Street to 11th Street,
  • 9th Street from “R” Street to “S” Street
  • and Sage Street in front of the Gering Medical Clinic.

Work shall include cold milling, asphalt overlay, and related work. Please refrain from parking on these streets during the specified timeframe.